Little's law

A rule from queueing theory: average lead time equals average work in progress divided by average throughput.

In more detail

Eighteen items in progress finishing at six per week gives a three-week lead time. Adding people raises both work in progress and throughput and leaves lead time unchanged; halving work in progress halves it. The lever is finishing, not starting.

Examples

lead time = 18 items / 6 per week = 3.0 weeks
1,200 messages draining at 50 a second: a new arrival waits 24 seconds.
200 threads at 50 ms serve 4,000 requests a second; at 200 ms the same traffic needs 800.